Law stated as at 08 Nov 2005 • England, Wales |
To illustrate: When I left Allen & Overy, I joined the London office of Sonnenschein Nath & Rosenthal. Sonnenschein was the principal external counsel for McDonalds. At the time, McDonalds was contracting to buy many sites, each contract being conditional on planning. The process, from finding a site, making an offer, obtaining the planning permission and other authorisations and opening, was considerably longer in England than in any other European jurisdiction. A new general counsel for McDonalds asked how we could improve the process. My response was to suggest that McDonalds should produce a reasonable contract. I had seen from previous deals that if McDonalds wanted a contract conditional on planning they would argue with the landowner over their draft for weeks, if not months. McDonalds' negotiators always imposed in the heads of terms that the starting point would be the McDonalds' form of contract. It was clear that there were a number of points in the McDonalds' form that landowners found very difficult to accept and which, in a significant number of cases, McDonalds would eventually concede. I suggested that McDonalds should start with a contract "straight down the middle", so that all we were only dealing with the actual site and deal specifics. Unfortunately, this did not find much favour. Shortly after, Sonnenscheins closed in London. I do not believe my idea was taken up but I still believe that it was the right solution. |
For information on title investigation, see:
|
In a recent conversation I had with a property director of a substantial pub business, about the need to sell on properties that were underperforming as pubs, the question arose whether the conditional sale contract was a mechanism that was much used. In that operator's view, the complexity of entering into a contract conditional on planning was not, in most cases, sufficiently attractive because there was little chance of a material increase in the resultant value. Out of a portfolio of 150 sales over the last two or three years, there had only been two sites where their disposal was conditional on planning. These were exceptionally more valuable than the average disposal figure, three times in one case, nine times in another. In most cases, the alternative use for an existing property was well known and the chances of a particular planning application being refused or conditions imposed, which would have a material effect on the value, were very small. There was little to justify the developer entering into a conditional sale contract. |
SDLT The charge to SDLT arises on the acquisition of a chargeable interest. The general rule is that there is no land transaction at the contract stage where the contract will be followed by a conveyance. Contract and conveyance are taken as parts of a single land transaction and the effective date for SDLT purposes is the date of completion (section 44(1)-(3), Finance Act 2003 (FA 2003)). As a general rule, the liability to SDLT will arise at completion and the Land Transaction Return and any SDLT due will have to be submitted or paid within 30 days of the date of completion. However, if the contract is "substantially performed" before it is completed, the date of substantial performance is taken as the trigger date and the Land Transaction Return and any SDLT due will have to be submitted or paid within 30 days of that date (section 44(4), FA 2003). A contract is substantially performed when either of the following occur:
(Section 44(5), FA 2003.) Whether there has been substantial performance will be a matter of fact and each case will be judged on its own merits. By structuring the document so that the obligations to buy and sell the property do not come into force until the planning condition precedent has been satisfied, (so that the buyer has no interest in the property until the planning condition precedent has been satisfied), the risk is reduced that HM Revenue and Customs will argue that there has been substantial performance of the contract based on either occupation or on the payment of the Initial Price [defined in the Standard document and Drafting note]. To be successful in establishing substantial performance, HM Revenue and Customs would have to show that one of the following:
For more information on SDLT and substantial performance, see:
|
Under the Taxation of Chargeable Gains Act 1992 (TCGA 1992), tax is paid in respect of any gains accruing on the disposal of assets, which are not taxable as income (they are "chargeable gains"). Tax on chargeable gains can be either capital gains tax (for individuals and trustees) or corporation tax on chargeable gains (for companies). There are special rules to determine when a disposal takes place (section 28, TCGA 1992). Section 28 does not deem there to have been a disposal, but merely states when the disposal is made, if at all (see Legal update, Capital gains tax: time of disposal).
If the contract is not conditional, the seller will be treated as having disposed of the property on exchange of contracts and will be required to account for tax due on any chargeable gain in the seller's tax year in which the disposal occurred:
If, on the other hand, the contract is conditional, the seller will be treated as having disposed of the property when the condition is satisfied (that is, when satisfactory planning permission is obtained). The cashflow and administrative difficulties are very largely avoided. |
There are two types of condition:
On the assumption that the parties will want the obligation to obtain planning permission to be a condition precedent, the Standard document aims to make it as clear as possible that the condition is indeed a condition precedent:
|
Further information
|
Effect of planning performance targets We live in an age where there are league tables for everything and there is a stick and carrot approach by central government to ensuring the appropriate delivery of services by local government. Local authorities are being given instructions by central government to speed up the planning process. This means making planning decisions on applications within the appropriate time limits. If those time limits are not met, the local authority gets a "black mark", and if they get too many black marks, the local authorities live in fear of having their government grants reduced or additional payments not made. As a member of the Planning and Environment Law Committee of the City of London Law Society, I have heard about a number of occasions where negotiations for planning have been unilaterally terminated by the planning authority even though everyone was extremely close to completing the negotiations. In these cases, the negotiations appear to have been terminated solely because there was a danger of the decision not being given within the time required, so triggering an adverse report back to the Office of the Deputy Prime Minister. This can often happen completely out of the blue because it is a management decision taken by managers in the planning group or by those having a finance function within the local authority, and nothing to do with the case officer or his immediate superiors. The local authorities are playing the rules to protect their position with regard to their grant entitlement. The fact that the applicant for planning permission suffers, does not matter as far as the local authority is concerned, but it will matter for the applicant, be the applicant the buyer or the seller. |
Drafting note: Contract for the sale of freehold land with vacant possession conditional on planning permission: Planning Application. Drafting note: Contract for the sale of freehold land with vacant possession conditional on planning permission: Planning application (clause 6). Drafting note: Contract for the sale of freehold land with vacant possession conditional on planning permission: Planning Appeal (clause 7). |
For further information on property and environmental investigation, see:
For further information on Environmental impact assessements, see Practice note, Environmental impact assessments and planning applications. |